References

Development of M100 highway between Esztergom and M1 motorway, Permit design (2019)

Client: Constreal Ltd.

The M100 motorway starts from the main road No. 1 in the area of Bicske, then it crosses the M1 motorway in a north, north-easter direction, later the main road No. 10, and then it reaches the border of Esztergom by widening the main road No. 117. The section is 32 km long, and more than 10 km of minor roads will be built. The vertical alignment of the line varies according to the topography of the area, the size of the embankments are greater than the usual earthworks, and there are also 15 to 20 m deep cuts in several places.

For the road construction the soil investigation report contains a total of 216 borehole logs and 36 static soundings. In a geotechnical design report, we covered the tasks involved in road construction, among others foundations of embankment, stability calculations, drainage, erosion protection, embankment settlement. Our assignment covered only the road construction tasks, for the structures planned on the section (tunnels, viaducts, underpasses, overpasses, buildings) a separate soil investigation report and geotechnical design report were made.